sankar9999
I am using Project 2003 and new to the product. Here's my situation.
I have setup a plan for my new project. Several of my resources have
other regular support tasks as well [Level of effort tasks]
Out of the 40 hrs per week, they have 15 hrs to take care of support
and another 5 hrs on other admin. That leaves me with the remaning 20
hrs per person for my new project.
Estimated hours for one of my tasks is 60 hrs. When I assign this
resource to the project task, it allocates 8 hours for the resource
each day. When I changed the percentage availability to 50%, it
changes the work hours to 30. I was expecting to see the work hours to
be kept at 60 and duration changed appropriately.
I am doing something wrong and could use your help. Appreciated.
Sanka
I have setup a plan for my new project. Several of my resources have
other regular support tasks as well [Level of effort tasks]
Out of the 40 hrs per week, they have 15 hrs to take care of support
and another 5 hrs on other admin. That leaves me with the remaning 20
hrs per person for my new project.
Estimated hours for one of my tasks is 60 hrs. When I assign this
resource to the project task, it allocates 8 hours for the resource
each day. When I changed the percentage availability to 50%, it
changes the work hours to 30. I was expecting to see the work hours to
be kept at 60 and duration changed appropriately.
I am doing something wrong and could use your help. Appreciated.
Sanka