Rate Change

G

George L

Hi - When the fiscal year changes in October 1, I need to change the rate my
client will be billed. Is there a way in project to change the rate at a
certain time without loosing the history of money already charged (or having
that $ value automatically change)?

Thanks,

George.
 
G

George L

Hi again - I figured out my own problem. If you go to the Resource Usage
view, double click on the resource name, select the Cost tab, you can enter
the rage structure there. You cannot change the Effective Data for the
first item in that list, so you need to add rates and dates to the list.

George.
 