Re-ordering numbered tasks

R

Robert

I have about 100 tasks. I moved them around and numbered them. I created a
mask, but numbers don't automatically go in although they are in the mask.
 
J

Jan De Messemaeker

Hi Robert,

I'm trying to imagine what you mean.
If this is about the formatted of the WBS field, go to Project, WBS,
renumber.
If not could you tell us what this is about?
Greetings,
 
J

JulieS

Hi Robert,

When you created the mask did you select the option "Generate WBS code
for new task"?

If you try Project > WBS > Renumber does the new number appear?

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top