Re-using old MPP files

P

Phil

Hi,

I'm trying to re-use and old project plan but I can seem
to get the dates to update!

Can anyone help me? I'm sure it's a two second fix but I
can't find it!

Thanx.
 
J

Jan De Messemaeker

Hi Phil,

1. Select all tasks, right-click, Task Information, set %complete to 0;
Advanced tab, constraint type, set to as soon as possible
2. (2002+) Analysis Toolbar, Adjust Dates
or (2000) Tools, Macro, Macros, Adjust_dates, Run

HTH
 