R
Raj Limaye
I assigned costs of different resources in the resource sheet, completed
schedule and saved the baseline.
The project is in progress and is continuously being tracked. The %complete
on several tasks have been entered.
The original cost data ($/hr) on the resource sheet was approximate. I got
the correct cost data from Accounting department halfway in the project. I
entered the correct values in resource sheet.
Now I want to calculate the baseline and earned value fileds using the newly
entered cost data. Is there a way?
I know the easy answer is to save a new baseline. However the new baseline
saves the snapshot of current Work values (which are different from the
original as the project progress was continuously updated with actula finish
date or %work comlete fileds)
I want the original Work values with new cost basis so that the earned value
analysis will be more meaningful.
schedule and saved the baseline.
The project is in progress and is continuously being tracked. The %complete
on several tasks have been entered.
The original cost data ($/hr) on the resource sheet was approximate. I got
the correct cost data from Accounting department halfway in the project. I
entered the correct values in resource sheet.
Now I want to calculate the baseline and earned value fileds using the newly
entered cost data. Is there a way?
I know the easy answer is to save a new baseline. However the new baseline
saves the snapshot of current Work values (which are different from the
original as the project progress was continuously updated with actula finish
date or %work comlete fileds)
I want the original Work values with new cost basis so that the earned value
analysis will be more meaningful.