Recalculate EV Fields

S

Sebastian Cordoba

Hello everyone.

I need to find a way to recalculate EV fields without overwriting an
existing baseline (which doesn't have costs). In order to get it, I've
developed a macro to assign a specific standard rate to the plan's resources
($1/hr) and then assign the new cost (calculated by Project) to the baseline
cost field of each task.

I assumed that all of the EV fields were going to be calculated by Project
as well, but it didn´t happen. Is there a method to do something like:
mytask.BCWS.recalculate()

Thanks for your help.
 