I am managing around 30 project plans where resources will not be working
full time.
So I have tested changing resource unts to 50% and trying this with the 3
possible task types.
What I want to happen is for Project to recalculate the duration of the task
based on the resource available units.
Is this possible?
So a 10day task becomes 20 days if the resource is only available for 50%
units.
Basically plans are in place, with work tracked already, I am putting in
standards for use on future plans, but have to deal with ones in progress
which I have just inherited.
Many thanks
full time.
So I have tested changing resource unts to 50% and trying this with the 3
possible task types.
What I want to happen is for Project to recalculate the duration of the task
based on the resource available units.
Is this possible?
So a 10day task becomes 20 days if the resource is only available for 50%
units.
Basically plans are in place, with work tracked already, I am putting in
standards for use on future plans, but have to deal with ones in progress
which I have just inherited.
Many thanks