P
pj
I have a recurring task which applies to all resources and it occurs for 10
hrs each week. I allocated it to Friday more for consistency than anything
else.
I have set up the task to recur and they are all at the top of the project
gantt chart. I need to get them sorted by date within the project and link
properly, with the last last task of each week being its predecessor but they
keep being pushed to the end of the project. Is there a different linking
process that needs to be done before sorting the tasks
Thanks
hrs each week. I allocated it to Friday more for consistency than anything
else.
I have set up the task to recur and they are all at the top of the project
gantt chart. I need to get them sorted by date within the project and link
properly, with the last last task of each week being its predecessor but they
keep being pushed to the end of the project. Is there a different linking
process that needs to be done before sorting the tasks
Thanks