V
Velson Horie
A contract I am setting up has to report every 3 months. This is then
followed up by a discussion within a week, then approval and payment.
First question. How do I set up a recurring task with a 3 month interval?
From the dialog box and previous posts, the answer is no. (If no, then
future Projects should have an option to choose the interval.)
At the moment I am setting these up by hand (for multiple contracts), and
having to change them everytime the start date changes.
Second. If yes, can I set up a recurring nest of tasks?
I am using Project 2003 SP1, XP SP2.
Thank you
followed up by a discussion within a week, then approval and payment.
First question. How do I set up a recurring task with a 3 month interval?
From the dialog box and previous posts, the answer is no. (If no, then
future Projects should have an option to choose the interval.)
At the moment I am setting these up by hand (for multiple contracts), and
having to change them everytime the start date changes.
Second. If yes, can I set up a recurring nest of tasks?
I am using Project 2003 SP1, XP SP2.
Thank you