I am just wondering is there an easy/standard way let the schedule move an
entire recurring task to a different start date. For example, Phase 2 has 1
meeting every week for two months and was originally due to start on 1/4/08.
The start of Phase 2 has a Finish Start dependency with the end of Phase 1.
Phase 1 is delayed by a month and hence the Start of Phase 2 is delayed, but
I don't see any obvious way of getting the recurring task to move out a month.
I can manually change the 'Range of Recurrence' 'Start' date but would like
this to automatically update when a schedule slippage occurs.
entire recurring task to a different start date. For example, Phase 2 has 1
meeting every week for two months and was originally due to start on 1/4/08.
The start of Phase 2 has a Finish Start dependency with the end of Phase 1.
Phase 1 is delayed by a month and hence the Start of Phase 2 is delayed, but
I don't see any obvious way of getting the recurring task to move out a month.
I can manually change the 'Range of Recurrence' 'Start' date but would like
this to automatically update when a schedule slippage occurs.