peter.mulford
Hi
I'm new to project so please bare with me if I'm using it all
wrong!
I have created a recurring task that happens every workday and lasts
for 30mins, and should end in a years time.
I have then added the person who should do the task on the resources
view. On the tasks view I have then chosen the person and replicated
their name down the list of recurring tasks.
However, when I now look at resource usage, the first row, that shows
the summary task for the person has 920.5h on the first day? The first
subtask shows 8hr and the second 0.5hr.
This seemed to mean that they were over allocated and could not be
That doesn't seem to make any sense to me. Can anyone explain it
please?
I basically wanted to show the daily recurring tasks such as meetings
etc, as well as tasks relating to completion of projects, to show where
people's time was being spent.
Thank you
I'm new to project so please bare with me if I'm using it all
wrong!
I have created a recurring task that happens every workday and lasts
for 30mins, and should end in a years time.
I have then added the person who should do the task on the resources
view. On the tasks view I have then chosen the person and replicated
their name down the list of recurring tasks.
However, when I now look at resource usage, the first row, that shows
the summary task for the person has 920.5h on the first day? The first
subtask shows 8hr and the second 0.5hr.
This seemed to mean that they were over allocated and could not be
That doesn't seem to make any sense to me. Can anyone explain it
please?
I basically wanted to show the daily recurring tasks such as meetings
etc, as well as tasks relating to completion of projects, to show where
people's time was being spent.
Thank you