What happens to the task when the assigned resource selects "Reject" task
after it has been complete? Does it remove this from their timesheet view?
If yes, it is also removed from the Project Schedule and Project Notification
process?
Thanks
KD
 
D

Dale Howard [MVP]

KD --

From your description, it sounds like the team member accidentally clicked
the Reject button when he/she meant to click the Hide button. Regardless,
when a team member rejects a task, the system temporarily hides the task
from the team member's timesheet in PWA, and the rejection update is sent to
the PM. The PM can then simply select the Reject option for this rejection
update and click the Update button. The system will put the rejected task
back on the team member's timesheet. If the team member doesn't want to see
the completed on his/her timesheet, he should select it and click the Hide
button. Hope this helps.
 