SHARIEF
Hi
In the resource usage view. Resource of type material distribution is
seen in decimals over a time scale. For example I have a material resource
called 8M/200kg PSC pole and the unit is in nos. Considering the task
duration the work is distributed as 20.12,20.22....... nos which appears to
be illogical. As a pole could not be in decimals like 0.1 pole. How to change
the work quantity in whole numbers only (correcting to nearest decimal).
In the resource usage view. Resource of type material distribution is
seen in decimals over a time scale. For example I have a material resource
called 8M/200kg PSC pole and the unit is in nos. Considering the task
duration the work is distributed as 20.12,20.22....... nos which appears to
be illogical. As a pole could not be in decimals like 0.1 pole. How to change
the work quantity in whole numbers only (correcting to nearest decimal).