Project 2007 SP1 Issue with Resource Units

K

klafollette

I applied Project 2007 SP1 over the weekend. I am working on an existing
project, and I see that I now have resources on tasks where the Units show
"0" in the task form, yet they have work. I see the work hours correctly in
resource/task usage. I currently have units expressed in decimal format. If I
switch to show percentage format, I see the resource is allocated 20% in the
task form, which is right for the work/duration. If I change it to show units
as a decimal, they again show it as "0" zero units. Seems like it is rounding
down or just not displaying the decimal.

I tried also by inserting "assignment units" column on the Task Usage view,
and it also shows resource at "0" zero units in decimal mode, but 20% in
percentage mode.

Anyone seen this, and is there a quick fix? I have hundreds of these entries
to deal with.

Kevin LaFollette
 
J

JulieS

klafollette said:
I applied Project 2007 SP1 over the weekend. I am working on an
existing
project, and I see that I now have resources on tasks where the Units
show
"0" in the task form, yet they have work. I see the work hours
correctly in
resource/task usage. I currently have units expressed in decimal
format. If I
switch to show percentage format, I see the resource is allocated 20%
in the
task form, which is right for the work/duration. If I change it to
show units
as a decimal, they again show it as "0" zero units. Seems like it is
rounding
down or just not displaying the decimal.

I tried also by inserting "assignment units" column on the Task Usage
view,
and it also shows resource at "0" zero units in decimal mode, but 20%
in
percentage mode.

Anyone seen this, and is there a quick fix? I have hundreds of these
entries
to deal with.

Kevin LaFollette
Hi Kevin,

I have Project Professional SP-1 installed and cannot reproduce what you
report. Does the issue happen with all project files or just one
specifically?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top