Hello All,
I am making a plan in which I set the leveling to manual. There are few
tasks in which the successor tasks start before the completion of
predecessor and I manually assigned the day usage via going to "Resource
Usage" for resources. Doing this make the resource overallocated even they
are well leveled and 100% allocated (i.e. 1 day). Can someone help me on
this? One way to avoid it is to level resources via "Automatic leveling"
option but this will shift the schedule ahead of delivery date.
Thanks in advance.
Regards,
Abid
I am making a plan in which I set the leveling to manual. There are few
tasks in which the successor tasks start before the completion of
predecessor and I manually assigned the day usage via going to "Resource
Usage" for resources. Doing this make the resource overallocated even they
are well leveled and 100% allocated (i.e. 1 day). Can someone help me on
this? One way to avoid it is to level resources via "Automatic leveling"
option but this will shift the schedule ahead of delivery date.
Thanks in advance.
Regards,
Abid