I am having a problem using MS Project 2002.

I have set up my project. I would like to create a report for all tasks
that are sure on a specific 'Finish' date. Thus I would like to create a
report that only contains the tasks that are due for completion on June 30,
2006.

I would also like to create a report on a Monday, that would provide me a
list of tasks that would be completed during the week cited. Thus I would
want to enter the date range: July 10 thru July 14 (Monday thru Friday). The
report would list all tasks that have a 'Finish Date' within the specified
five day date range regardless of the 'Start' date.
 
R

Rod Gill

Hi,

Select Project, Filtered for, Auto Filter

Click the black triangle in the Finish column's title. Choose this week for
this week report. For finish on a specific day click Custom and enter the
date.
 