Hi,

I am trying to find a way to generate a report from a project that looks
like the following:

---
Resource A:
Task A1 [Start/Finish Dates, etc]
Task A2 [Start/Finish Dates, etc]

Resource B:
Task B1 [Start/Finish Dates, etc.]
Task B2 [...]

Resource C:
etc...
---

Where the Tasks for each resource are sorted by Start date.

Is there a way to do this?

Thanks
Brian
 
J

John

Brian Ross said:
Hi,

I am trying to find a way to generate a report from a project that looks
like the following:

---
Resource A:
Task A1 [Start/Finish Dates, etc]
Task A2 [Start/Finish Dates, etc]

Resource B:
Task B1 [Start/Finish Dates, etc.]
Task B2 [...]

Resource C:
etc...
---

Where the Tasks for each resource are sorted by Start date.

Is there a way to do this?

Thanks
Brian

Brian,
Try the Resource Usage view sorted by Start Date.

Hope this helps.
John
Project MVP
 
J

JulieS

Hi Brian,

I assume you have found the Who Does What Report and discovered the fact
that the report doesn't sort the assignments by Start Date.

The work around that I use as suggested by John is the resource usage view
with the Start and Finish date added to the table (left side) and then
sorted by Start date. I then hide the right side (timescaled portion) of
the view.

I hope this helps. Let us know how you get along.

Julie
 