Hi:

I want to create a report that shows tasks that are supposed to be finished
by a specific date - it would be great if it could exclude tasks that are
100% done.

I am trying to see what tasks are due this week, next week etc.

Thanks in advance.
 
G

Gérard Ducouret

Hello,

In Project, create a new filter : Project / Filtered For / More Filters.../
New
Field Name : Finish
Test : is within
Values : one date, list separator, another date
AND
Field : % complete
Test : is less than
Values : 100%

Hope this helps,

Gérard Ducouret
 
L

Ldyflyr

That was good thanks for the quicky reply

Gérard Ducouret said:
Hello,

In Project, create a new filter : Project / Filtered For / More Filters.../
New
Field Name : Finish
Test : is within
Values : one date, list separator, another date
AND
Field : % complete
Test : is less than
Values : 100%

Hope this helps,

Gérard Ducouret
 