Report Help

S

scott.siegler

Hello,

I am trying to come up with a report with only a list of all the tasks
and the start and finish date for each. Is it possible to do this?
None of the reports I see seem to allow this.

Ideally, I would like a report where I pick only certain tasks and have
the report show these tasks and the start and finish dates. Is this
possible?

thanks,
Scott
 
P

Project Slave

Two stage process:
1. Create a new table with only the relevant fields
2. Generate a report out of this new table

Step by step: (Create new table)
View > Table > More table
Select Task Table -> Entry
Select Copy (to say 'Task Report Table')
Edit 'Task Report Table' - remove unwanted fields

(Report)
View > Report > Custom Report
Select Task Report Table
Generate Report
 
J

JulieD

Hi Scott

wouldn't bother with a "report" per se, i would just use the Task Sheet view
(view / more views / task sheet) then as it's better to create a new table
rather than modify the existing tables i would choose view / table: entry /
more tables / copy - call the new table "Report Table" and then delete the
rows that i don't want to see in the print out ... (also tick show in menu)
.... once the tables have been deleted click OK and APPLY. This table will
now be shown in the Task Sheet view ... now use the Autofilter or filter box
to filter out the tasks you don't want to see (if you're doing this on a
regular basis you can insert a new column and filter based on that) and then
print it out.

Hope this helps
Cheers
JulieD
 