M
Micheal
Hi,
(1) When we open reports dialog box and select Assignments and select the
Who Does What When and click on Edit button and change the setting to Dates
Range.
but at run time when we applied different dates and click ok . the report is
not generating at the specified dates . whether the report is displaying
from the beginning.date of the project.
(2) When we select multiple project from the project web access (Project
centre) and open in the project professional and want generate report of
three to four months then the dialog box of low memory error is generated .
Tell me what is the limit of project professional 2003 to generate reports.
Regards
Micheal
(1) When we open reports dialog box and select Assignments and select the
Who Does What When and click on Edit button and change the setting to Dates
Range.
but at run time when we applied different dates and click ok . the report is
not generating at the specified dates . whether the report is displaying
from the beginning.date of the project.
(2) When we select multiple project from the project web access (Project
centre) and open in the project professional and want generate report of
three to four months then the dialog box of low memory error is generated .
Tell me what is the limit of project professional 2003 to generate reports.
Regards
Micheal