Hi Jackie,
Well, not exactly. You could certainly modify the To-Do List report
and base it on another table that doesn't show the Resource Names
field. However, the same task will appear on the reports for
different resources if there is more than one resource assigned. Let
me know if you want to pursue this option and we can get into specific
step-by-step details if you need them.
Bear in mind that the information shown on the To-Do List report is
showing when a *task* is scheduled to begin and end. Particularly in
the case of tasks with several resources assigned, a resource may not
necessarily start and end his/her assignment on the start date of the
task. A resource's assignment may be delayed or the resource may
finish his/her work on the assignment before the task is finished.
Perhaps if you could let us know specifically what you want to keep
from the To-do list report and what you want to omit, we can help
further. Have you looked at the Who Does What report? That report
could be modified to allow you to chose only a single resource as
well.
I hope this helps. Let us know how you get along.