Terri
I'm a new user of MS Project and need to set up a report from the resource
pool to show the % allocation per resource by week or month. I've started
with a new resource pool and attached a test project file to it that has some
tasks occurring in January and February 2006. I believe the Who Does What
When report will give me wha i need, but after setting the guidelines and
filters (no matter which I try), I can only get the report to show this week
or the month of November. Is there a setting in the pool I need to change?
Any help appreciated.