D
DanG
I have two resources who must both be present to work on a task. For example,
I have a mover, and a truck. The mover is available to work 8 hours each day.
The truck is only available four hours each day. It will take 32 hours of
work to complete the task (16 hours each, four days duration). The trucker
can work on other tasks when the truck is not available, and shouldn't be
working on this task when the truck is not available. How do I accomplish
this so I get the correct Work and Duration?
Thanks!
I have a mover, and a truck. The mover is available to work 8 hours each day.
The truck is only available four hours each day. It will take 32 hours of
work to complete the task (16 hours each, four days duration). The trucker
can work on other tasks when the truck is not available, and shouldn't be
working on this task when the truck is not available. How do I accomplish
this so I get the correct Work and Duration?
Thanks!