An Activity has working for 3 days, I have two resources.I want to allocate
the first resource for 1st day and the 2nd & 3rd day i want to allocate the
another resource. How can i allocate the resource by this method. Hope u will
help in this....
Tnx.....
 
R

Rod Gill

Simplest way is to assign the two resources to your task, then Click View,
Task Usage and edit the hours for each day of the duration.

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: www.projectvbabook.com
 
K

karthick

Ya i know this method to edit the hours, Then tell about the usage about
Resource Availabity in resoure sheet field.. I dont know how to use the
resource availbility from start and end.. plz give me detiail.
 
R

Rod Gill

From what you said you want, set work to 8h for day1 and 0h for day 2 and 3
For the second resource set work to 0h for day 1 and 8h for day 2 and 3

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top