Monica A.
I have a project plan which changes as I change my PC! On the work computer,
when I assign two resources 100% of their time to tasks, say of duration of
11 weeks, it doubles the duration of the task to 22 weeks. I have checked the
task information box and its settings are Fixed Unit and Effort Driven.
However, when I e-mail the mpp file to myself and access it on my home
laptop, it ends up working fine i.e. the duration drops to 1/2.
Do I have an issue with the settings on the two versions of MS Project?
Any help is highly appreciated!
when I assign two resources 100% of their time to tasks, say of duration of
11 weeks, it doubles the duration of the task to 22 weeks. I have checked the
task information box and its settings are Fixed Unit and Effort Driven.
However, when I e-mail the mpp file to myself and access it on my home
laptop, it ends up working fine i.e. the duration drops to 1/2.
Do I have an issue with the settings on the two versions of MS Project?
Any help is highly appreciated!