P
PhilippeG
Hi,
I have fixed work tasks to which I would like to allocate resources (at
100% of their time) but only for part of the duration of the task.
For example:
Task1 is worth 20 days of work. I assign 100% of my first resource
-Tom- to it as well as 100% of my second resource -****. The task will
therefore take 10 days to execute.
I also know that my third resource (yes - Harry), will become available
for 3 days after Task1 has started.
How do I reflect that? As soon as I assign Harry, he is assigned from
first to last day. how do assign Harry for 3 days only (he starts after
Tom and ****) and also needs to come off Task1 before they do.
Of course, I would expect that Task1's duration would decrease as a
result of having a 3rd resource working on it, even if it's only for a
few days).
I have attempted to manipulate allocated hours in the resource usage,
but that doesn't appear to be way to go as it has no impact whatsoever
on the task's duration.
I have fixed work tasks to which I would like to allocate resources (at
100% of their time) but only for part of the duration of the task.
For example:
Task1 is worth 20 days of work. I assign 100% of my first resource
-Tom- to it as well as 100% of my second resource -****. The task will
therefore take 10 days to execute.
I also know that my third resource (yes - Harry), will become available
for 3 days after Task1 has started.
How do I reflect that? As soon as I assign Harry, he is assigned from
first to last day. how do assign Harry for 3 days only (he starts after
Tom and ****) and also needs to come off Task1 before they do.
Of course, I would expect that Task1's duration would decrease as a
result of having a 3rd resource working on it, even if it's only for a
few days).
I have attempted to manipulate allocated hours in the resource usage,
but that doesn't appear to be way to go as it has no impact whatsoever
on the task's duration.