I have to allocate a resource which is different that the normal ones.

Slab forms - This is a set of forms which:
1. Required 3 days for installation
2. Beyond these 3 days, other activities like reinf binding & casting
needs to be done
3. After the casting activity, the concrete cast needs to attain
strength - 7 days after casting
4. Then these forms can be dismanatelled and reused

I need to allocate resource for this - say a set of 1500 sqm.

How do i do this by having a single task
 
J

Jim Aksel

Here's one method, but it is not recommended.

You would need to put a long duration task on one line implying all the
activities in the name:

Create 1500 sq m concrete Module

duration 20 days (or whatever). Assign resources as needed. Open the Task
Usage View and manually re-key the worker effort to the days desired. You
may need to use fixed duration as the task type.

Suggestion: Make a "module" of the tasks. Indent all the subtasks needed
under a heading which will make it a summary. Assign resources as required
to appropriate subtasks


--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top