I have to allocate a resource which is different that the normal ones.
Slab forms - This is a set of forms which:
1. Required 3 days for installation
2. Beyond these 3 days, other activities like reinf binding & casting
needs to be done
3. After the casting activity, the concrete cast needs to attain
strength - 7 days after casting
4. Then these forms can be dismanatelled and reused
I need to allocate resource for this - say a set of 1500 sqm.
How do i do this by having a single task
Slab forms - This is a set of forms which:
1. Required 3 days for installation
2. Beyond these 3 days, other activities like reinf binding & casting
needs to be done
3. After the casting activity, the concrete cast needs to attain
strength - 7 days after casting
4. Then these forms can be dismanatelled and reused
I need to allocate resource for this - say a set of 1500 sqm.
How do i do this by having a single task