P
Plunk
I'm new to project and am struggling with how to set things up on a
particular project. I've reviewed Mike Glen's tutorials, which ROCK, and have
helped me combine several into a master. LOVE IT.
OK - Here's the story:
I have three test sites and hundreds of tasks. Certain tasks are already
scheduled for each test site. There are many tasks that don't have a test
site assigned yet. To further complicate things, each test site has
increasing capabilities. For example, tasks that can be done in "C" can also
be done in "A" and "B". Tasks that can be done in "B" can also be done in
"A", but not "C". Tasks for "A" can only be "A".
In the end, I want to have a view with the three test sites and their
scheduled tasks. I'd also like to see the unassigned tasks and their required
test site(s).
Currently, I have three test sites as summaries, with their scheduled tasks
below. Additionally, I have an "unassigned" summary, with tasks. I was trying
to use the "resource" column and not getting anywhere . . . since the
resource is also a heading, I couldn't make it "connect". . . .
Is there a better way to set this project up? Should I be using assignments
and resources and linking them??
Thanks!
-- Plunk
particular project. I've reviewed Mike Glen's tutorials, which ROCK, and have
helped me combine several into a master. LOVE IT.
OK - Here's the story:
I have three test sites and hundreds of tasks. Certain tasks are already
scheduled for each test site. There are many tasks that don't have a test
site assigned yet. To further complicate things, each test site has
increasing capabilities. For example, tasks that can be done in "C" can also
be done in "A" and "B". Tasks that can be done in "B" can also be done in
"A", but not "C". Tasks for "A" can only be "A".
In the end, I want to have a view with the three test sites and their
scheduled tasks. I'd also like to see the unassigned tasks and their required
test site(s).
Currently, I have three test sites as summaries, with their scheduled tasks
below. Additionally, I have an "unassigned" summary, with tasks. I was trying
to use the "resource" column and not getting anywhere . . . since the
resource is also a heading, I couldn't make it "connect". . . .
Is there a better way to set this project up? Should I be using assignments
and resources and linking them??
Thanks!
-- Plunk