Hello all,
I'm interested in any feedback you can provide on the following
issue...it may take a bit to explain. I have a project that is using
a resource pool to pull the project's resources. I open the mpp file
and then select "do not open other files."
I have two different resources, both are showing different resource
IDs in both the resource sheet and resource pool. However, when you
pull up either of the resource calendars, they're sharing the same
calendar. Example: Resource A is taking a month off, so I'm going into
the plan to update her month as "non-working time." When you pull up
Resource B's Calendar, it shows Resource A's non-working time. The
same behavior is created when entering time in Resource B's calendar.
How do I overcome this?
They're both using the standard base calendar.
I'm interested in any feedback you can provide on the following
issue...it may take a bit to explain. I have a project that is using
a resource pool to pull the project's resources. I open the mpp file
and then select "do not open other files."
I have two different resources, both are showing different resource
IDs in both the resource sheet and resource pool. However, when you
pull up either of the resource calendars, they're sharing the same
calendar. Example: Resource A is taking a month off, so I'm going into
the plan to update her month as "non-working time." When you pull up
Resource B's Calendar, it shows Resource A's non-working time. The
same behavior is created when entering time in Resource B's calendar.
How do I overcome this?
They're both using the standard base calendar.