Resource Calendar pulling another resource's calendar

A

ashley.usher

Hello all,

I'm interested in any feedback you can provide on the following
issue...it may take a bit to explain. I have a project that is using
a resource pool to pull the project's resources. I open the mpp file
and then select "do not open other files."

I have two different resources, both are showing different resource
IDs in both the resource sheet and resource pool. However, when you
pull up either of the resource calendars, they're sharing the same
calendar. Example: Resource A is taking a month off, so I'm going into
the plan to update her month as "non-working time." When you pull up
Resource B's Calendar, it shows Resource A's non-working time. The
same behavior is created when entering time in Resource B's calendar.
How do I overcome this?

They're both using the standard base calendar.
 
M

Mike Glen

Hi Ashley,

Welcome to this Microsoft Project newsgroup :)

Don't know about this one :( Have you tried it with the other files opened?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top