I
Ian McCullough
I have a resource that works 24 hours per day, but needs manual labor to be
started ans topped, therefor I need a calendar that works 24 hours, but does
NOT allow the resource to end or start a task during the weekends. Is this
possible, or do I need to schedule tasks like that manually?
Many thanks
Ian
started ans topped, therefor I need a calendar that works 24 hours, but does
NOT allow the resource to end or start a task during the weekends. Is this
possible, or do I need to schedule tasks like that manually?
Many thanks
Ian