Resource callendar

I

Ian McCullough

I have a resource that works 24 hours per day, but needs manual labor to be
started ans topped, therefor I need a calendar that works 24 hours, but does
NOT allow the resource to end or start a task during the weekends. Is this
possible, or do I need to schedule tasks like that manually?

Many thanks
Ian
 
S

Shiv

Hi Ian,

You need to change your project calendar to 24 hours. From the main menu, go
to Project / Project Information and in the 'Calendar' dropdown list, choose
'24 Hours'. Weekends are still not included.

HTH
Shiv
 
C

catprasanna

Can't the calendar be set that week ends or holidays, so any assigment
on weekends moves out?

May be way out of target... but could help also!
 
I

Ian McCullough

Hey Shiv,
I thought about that but it is NOT what I want, since it doesn't count the
hours that it COULD do it's thing during the weekend.


Thanks
Ian
 