Resource constraint

B

Benoit Gantaume

Hi,
I would like to do something very simple: how to add some kind of resource
constraint?
For example, I have task 1 (priority 100) and task 2 (priority 200) and I
have allocated the same resource to both tasks. I will get a resource
overload. Fine.
Now how do I tell him: automatically reorganize the gant diagram according
to the priority knowing that the resource is fixed?

Thanks a lot for your help.
Best Regards,
 
G

Gérard Ducouret

Hi Benoit,

Tools / Level Resources...
In the Resource Leveling dialog : Leveling Order = Priority, Standard
Then click the Level Now button

Gérard Ducouret
 