hello,

I have created Machinery as a resource. & for this machinery, after working
on it for 10hrs, we have to stop it for 2 hrs before it can be restarted for
use again.

Is there any way to set a shelf declare contour that do that?
 
J

John

th said:
hello,

I have created Machinery as a resource. & for this machinery, after working
on it for 10hrs, we have to stop it for 2 hrs before it can be restarted for
use again.

Is there any way to set a shelf declare contour that do that?

th,
Yes, you can create any user contour you want by directly editing the
Work in either the Resource or Task Usage views. However, in your case,
it might be easier to create separate tasks - one for each operational
period with a 2 hour down time lag between operational periods.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top