Kevin Bennie
I have 15-20 projects using one resource pool.
While assigning one particular resource, let's call him Bob (I have only
experienced this error while trying to assign Bob) to a task I receive the
following error message:
"The resource is asigned outside the original dates for task 123 ----- in
project 'Bob's project'.
The duration of this fixed-duration task will change to accomodate the
resource assignment."
If I choose to continue to assign Bob and readjust my duration to it's
original amount, Bob has 0 work hours and duration will adjust if I try to
add any work.
If I assign another person along with Bob to a task and again (after
receiving this error) adjust the duration to it's original amount, I can add
work but only the other resource will have hours added.
The tasks attempting to assign Bob to have no % complete (which is a common
issue). Any ideas?
While assigning one particular resource, let's call him Bob (I have only
experienced this error while trying to assign Bob) to a task I receive the
following error message:
"The resource is asigned outside the original dates for task 123 ----- in
project 'Bob's project'.
The duration of this fixed-duration task will change to accomodate the
resource assignment."
If I choose to continue to assign Bob and readjust my duration to it's
original amount, Bob has 0 work hours and duration will adjust if I try to
add any work.
If I assign another person along with Bob to a task and again (after
receiving this error) adjust the duration to it's original amount, I can add
work but only the other resource will have hours added.
The tasks attempting to assign Bob to have no % complete (which is a common
issue). Any ideas?