G
GBARR
How do I override the resource hours that has a duration longer than resource
hours.
i.e.
Duration = Start-5/1/09, End 5/25/08
Resource Hours = 30
Basically indicating that a person only needs 30 hours to complete a task
but duration is set for a much longer time to account for waiting for
responses from 3rd party vendor.
hours.
i.e.
Duration = Start-5/1/09, End 5/25/08
Resource Hours = 30
Basically indicating that a person only needs 30 hours to complete a task
but duration is set for a much longer time to account for waiting for
responses from 3rd party vendor.