My project plan includes resources from my team and the cutomer's team.
I've been asked to resource level just my team.
Is there a way to separate out the resources by their team and only resource
level one category / team of resources?
 
J

JulieS

Hi H,

Insert the "Can Level" field into the resource sheet and set your
customer's resources to "No".

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 