D
Dave Williams
Hi all, sorry if this is a simple question but I can't find the answer in
the help. I've just started using Project and it seems quite neat apart from
this one blocker.
I have a resource person that's 50% busy for the whole of December, so I've
marked a fixed task across all of december using 50% of his resources. The
task is "must start on" to prevent it being rescheduled.
I then want him to do a task which will start in mid-november and run into
december. If I mark him as 100% work on the new task, Project won't schedule
any of that task in december, it will use a dotted line instead. If I mark
him as 50% for the task, it will be scheduled okay but it will allow him to
be 50% idle in november.
I want to be able to say that all his available resource should be used on
the task - 100% in november, 50% in december. I don't want to create two
tasks because then I can't use resource leveling at all.
Am I missing something obvious? Should I not be using a task to reserve 50%
of his time in December?
Thanks for any tips!
the help. I've just started using Project and it seems quite neat apart from
this one blocker.
I have a resource person that's 50% busy for the whole of December, so I've
marked a fixed task across all of december using 50% of his resources. The
task is "must start on" to prevent it being rescheduled.
I then want him to do a task which will start in mid-november and run into
december. If I mark him as 100% work on the new task, Project won't schedule
any of that task in december, it will use a dotted line instead. If I mark
him as 50% for the task, it will be scheduled okay but it will allow him to
be 50% idle in november.
I want to be able to say that all his available resource should be used on
the task - 100% in november, 50% in december. I don't want to create two
tasks because then I can't use resource leveling at all.
Am I missing something obvious? Should I not be using a task to reserve 50%
of his time in December?
Thanks for any tips!