It sounds like you reduced the maximum availability in the resource sheet
instead of editing the assignment percentages for the specific tasks.
Reducing max avail will NOT change the level of existing asssignments. It
will affect the default assignment for new tasks assignments and also sets
the level at which Project considers the resource to be overallocated.
Resource leveling will NEVER change the resource assignments, all it does is
*delay* work. So if I have someone on a task at 100%, and reduce the max
avail to 50%, and then try to resource level, Project will not reduce the
assignment and change the duration of the task because leveling doesn't make
those sorts of changes. Also there is no way Project can "slide" that task
back and forth in the calendar to resolve the overallocation, hence the
error message. By selecting the task and opening the resource assignment
dialog, you can edit the assigment from 100% down to 50% and you'll see the
duration does change the way you expect.
--
Steve House
MS Project MVP
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Shawn said:
MP2K - I have developed a series of tasks sequentially and now want to do
a cost comparison. For the second analysis, I tried to reduce my single
resourece assigned to all the tasks to 50%. My goal is for Project to level
the tasks by simply extending their start/finish dates. However, I can not
get project to level, I get the "The overallocation cannot be resolved
message" which suggest that I should either reduce the assigned units or
increase the Resource Availability. How can I get Project to simply push
the finish date to the right?