I've setup a hammock task for "Project Management" and I've been able to
setup a resource in other PM tools that only takes up 2 hours per day. How
would I do that in MS Project 2002? The same resource could be utilized for
the full 8 hours/day in other tasks but with regard to Project Management I
only want to allocate 2 hours/day.
Thanks,
Richard.