Brianp2001
I have a simple project with four 1 hour tasks that need to be
completed on the same day. The tasks can be done in any order and need
to be completed by the same resource. The work is 1 hour and the
duration is 1 hour. When I assign my resource to the 4 tasks, Project
shows my resource as over allocated. My resource has an availability
of 8 hours of work in a day. So, 4 hours of work in a day should not
show my resource as over allocated. By changing the resources units
for the tasks, changes my work or duration which it shouldn't. He will
be allocated 100% to each 1 hour task. I would agree that if Project
thinks the time of each task is at 9:00 am he would be over allocated,
but project assigns start and finish in day intervals and the exact
hour the resource completes the tasks doesn't matter, just that they
are completed in that day.
Anyone have a solution for this scenario?
completed on the same day. The tasks can be done in any order and need
to be completed by the same resource. The work is 1 hour and the
duration is 1 hour. When I assign my resource to the 4 tasks, Project
shows my resource as over allocated. My resource has an availability
of 8 hours of work in a day. So, 4 hours of work in a day should not
show my resource as over allocated. By changing the resources units
for the tasks, changes my work or duration which it shouldn't. He will
be allocated 100% to each 1 hour task. I would agree that if Project
thinks the time of each task is at 9:00 am he would be over allocated,
but project assigns start and finish in day intervals and the exact
hour the resource completes the tasks doesn't matter, just that they
are completed in that day.
Anyone have a solution for this scenario?