W
wolf
I have a fixed amount of work (e.g. 100 days) ,which needs to be done
within the next 10 month. Now I want to split this work beteen 2
resources.
Resource A should work 60 days
Resource B should work 40 days
How can I do this in project without changing the total of 10 months?
within the next 10 month. Now I want to split this work beteen 2
resources.
Resource A should work 60 days
Resource B should work 40 days
How can I do this in project without changing the total of 10 months?