Resource Pool Task Lists

R

Ryan P

I am using a master project and a resorce pool to manage all of our projects.
What I now need to do is print out task lists for specific individuals on a
weekly basis.

I have been able to filter by name, but it shows all the tasks that are 100%
done. I do not want them on the list, only the ones that are still not
complete. When I try and filter by that column too, I only get the entry for
the resource pool itself, not any of the sub projects.

Any ideas how I can do this?
 
J

John

Ryan P said:
I am using a master project and a resorce pool to manage all of our projects.
What I now need to do is print out task lists for specific individuals on a
weekly basis.

I have been able to filter by name, but it shows all the tasks that are 100%
done. I do not want them on the list, only the ones that are still not
complete. When I try and filter by that column too, I only get the entry for
the resource pool itself, not any of the sub projects.

Any ideas how I can do this?

Ryan,
I just tried what I understand you want on a sample master file with a
separate resource pool. Everything worked fine whether the resource pool
file was open or not. I used the following filter (I happened to make it
interactive for ease of testing with different resource names).

And/Or Field Name Test Value(s)
Resource Names Contains "Who"?
And % Complete is less than 100%

In order to help you we need more information about your exact file
structure and your filter.

John
Project MVP
 