C
Cheryl
I have created a resource pool for each department in my
organization. I have also created a master resource pool
which contains inserted projects for each department. I
want to be able to report on all resources across the
organization to exec mgmt. When I try to export time
scaled data to excel, I get an error msg that
states "There are no resources in the current project. Try
again after the project has one or more resources." What
have I missed? I don't want to combine all the resouces
into one huge resource pool, because this will cause
confusion at the department level. All suggestions,
comments welcome. BTW, I am using Proj Std 2002.
Thanks in Advance,
Cheryl
organization. I have also created a master resource pool
which contains inserted projects for each department. I
want to be able to report on all resources across the
organization to exec mgmt. When I try to export time
scaled data to excel, I get an error msg that
states "There are no resources in the current project. Try
again after the project has one or more resources." What
have I missed? I don't want to combine all the resouces
into one huge resource pool, because this will cause
confusion at the department level. All suggestions,
comments welcome. BTW, I am using Proj Std 2002.
Thanks in Advance,
Cheryl