I need some help understanding how resources work and baseline work roll up
in the resource usage view. Here is the process: (we are using Project 2000)
We saved 3 tasks all done by the same resource that were under a summary bar
and the summary bar to a baseline. Total hours and baseline hours were 240
hours when you viewed the resource usage view.
Next we added another task for the resource under the summary bar and saved
just that task as a baseline. Now if you view the resoruce usage view for
the resource. The baseline work for that resource is 240 hours, but the work
is 320 hours.
If you look at the task usage view you see the same difference. This is
what I have seen before. However I would expect the resource usage view to
not have this behavior. Is this correct? How does project calculate the
resource summary information?
thanks.
in the resource usage view. Here is the process: (we are using Project 2000)
We saved 3 tasks all done by the same resource that were under a summary bar
and the summary bar to a baseline. Total hours and baseline hours were 240
hours when you viewed the resource usage view.
Next we added another task for the resource under the summary bar and saved
just that task as a baseline. Now if you view the resoruce usage view for
the resource. The baseline work for that resource is 240 hours, but the work
is 320 hours.
If you look at the task usage view you see the same difference. This is
what I have seen before. However I would expect the resource usage view to
not have this behavior. Is this correct? How does project calculate the
resource summary information?
thanks.