S
snetzky
I am having a problem with the way Project is scheduling my resources.
Is there a way to force Project to schedule task resources for the same
time period?
My example is this:
I have a fixed duration task where a crew is using a forklift to
perform a job.
I have 6 forklifts available round the clock (600% on the resource
sheet on a 24 hour shift) and a day and a night crew (100% on a 12 hour
shift: 6A-6P or 6P-6A).
On my task, I have two resources: day crew and fork lift, both at 100%
for 4 hours or a total of 8 hours of work.
8 hours work / 2 units = 4 hours duration
However, the @#%$@%@$# application insists on scheduling my two
resources at two different shifts which is not terribly useful.
Do I have to split the forklifts up to a day and night set also? That
seems a gigantic pain to me.
Larry
Is there a way to force Project to schedule task resources for the same
time period?
My example is this:
I have a fixed duration task where a crew is using a forklift to
perform a job.
I have 6 forklifts available round the clock (600% on the resource
sheet on a 24 hour shift) and a day and a night crew (100% on a 12 hour
shift: 6A-6P or 6P-6A).
On my task, I have two resources: day crew and fork lift, both at 100%
for 4 hours or a total of 8 hours of work.
8 hours work / 2 units = 4 hours duration
However, the @#%$@%@$# application insists on scheduling my two
resources at two different shifts which is not terribly useful.
Do I have to split the forklifts up to a day and night set also? That
seems a gigantic pain to me.
Larry