Hi,
I am adding (manually) resources in a resource sheet view.
I have customized the view to display the Available from/to date columns.
In the "Resource Information " dialog, I specify the Available from/to
dates, to reflect resource availability during the project lifecycle.
Resources are not yet assigned to tasks.
When I close the "Resource Information" dialog, the available from/to dates
shown in the "resource sheet" view are different than the one I specified
(most of them are N/A). I noticed that this behavior only happens for
resources that have a "Available from" date greater than today.
If I re-open the "Resource Information" dialog, the from/to dates are
correctly shown.
Am I doing anything wrong?
Thanks for your help
Marco
I am adding (manually) resources in a resource sheet view.
I have customized the view to display the Available from/to date columns.
In the "Resource Information " dialog, I specify the Available from/to
dates, to reflect resource availability during the project lifecycle.
Resources are not yet assigned to tasks.
When I close the "Resource Information" dialog, the available from/to dates
shown in the "resource sheet" view are different than the one I specified
(most of them are N/A). I noticed that this behavior only happens for
resources that have a "Available from" date greater than today.
If I re-open the "Resource Information" dialog, the from/to dates are
correctly shown.
Am I doing anything wrong?
Thanks for your help