M
Marni
I am working on a Project plan that contains fixed work tasks. I entered the
tasks and then entered the work hours for all of the tasks. Now I am going
through and assigning resources to the tasks.
(All of my resources are full time employees, but have only part of their
week to devote to this project, so I have set them up in the resource table
with less than 100% unit availability.)
Most of the tasks on my project have more than one resource working on them,
many with varying amounts of work on each task. For example -- a 100 hour
task with 2 resources - one working 80 hours, the other working 20. Whenever
I add resources to my tasks, the % units that appears in the Task Entry sheet
(and beside their name on the gannt chart) is not always the % units that
they have available for the project. Sometimes it is 267% or 1667% and the
finish date of the task doesn't change, as I would expect it to with
effort-driven scheduling. Shouldn't Project list their available units and
adjust the finish dates when I add resources to a task?
tasks and then entered the work hours for all of the tasks. Now I am going
through and assigning resources to the tasks.
(All of my resources are full time employees, but have only part of their
week to devote to this project, so I have set them up in the resource table
with less than 100% unit availability.)
Most of the tasks on my project have more than one resource working on them,
many with varying amounts of work on each task. For example -- a 100 hour
task with 2 resources - one working 80 hours, the other working 20. Whenever
I add resources to my tasks, the % units that appears in the Task Entry sheet
(and beside their name on the gannt chart) is not always the % units that
they have available for the project. Sometimes it is 267% or 1667% and the
finish date of the task doesn't change, as I would expect it to with
effort-driven scheduling. Shouldn't Project list their available units and
adjust the finish dates when I add resources to a task?