A
AMH
Why is it that when looking at the Resource Usage view
using MSP Pro 2003 - if you do not have the project plan
open the data that shows up for assigned work isn't
always correct? For example I have project 1 open, but
the resource is also assigned to project 2. Under the
project 2 heading the work assigned shows 6 when it is
actually 2.5?? Only when I actually open both project 1
and 2 do the numbers show up correctly. We were told this
is a known bug? Is there a hot fix for this?
This makes if very difficult for our managers to level
their resources. Thanks!
using MSP Pro 2003 - if you do not have the project plan
open the data that shows up for assigned work isn't
always correct? For example I have project 1 open, but
the resource is also assigned to project 2. Under the
project 2 heading the work assigned shows 6 when it is
actually 2.5?? Only when I actually open both project 1
and 2 do the numbers show up correctly. We were told this
is a known bug? Is there a hot fix for this?
This makes if very difficult for our managers to level
their resources. Thanks!