Resource Usage Report Summarised by Outline Level and Resource Group

D

dxd

Project 2003
==========

I want to be able to have a report, I think the Resource Usage is the
place to do this, that shows me at the activity level, just Outline
Level 1 summaries, and then within that I want to know the work by
Resource Group.

So for example I want to see :-

Phase 0
Customer 25 days
Supplier 30 days
Phase 1
Customer 13 days
Supplier 12 days


But I'm struggling, if I do the Customize Group By and group by Task
Outline Number, then Group I get all of the outline levels, not just
Outline Level 1, and I can't seem able to use the "Define Groups
Intervals...." to get what I want.

Suggestions?


Thanks


David
 
M

Mike Glen

Hi David,

Welcome to this Microsoft Project newsgroup :)

When you've grouped, try clicking the Show button on the formatting toolbar
and selecting the outline number you want.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top