trev
Hello,
I'm just getting to know Project 2000 and have set up a
master resource file that is separate from my project
files.
While trying different scenarios from my project folders,
I usually have the screen split to view the gantt chart
and the resource usage view.
The resource usage is set for Work and Actual Work. There
are times when I move the work hours to another date for a
resource leveling scenarios (tweaking). There are other
times when I try this and the figure that insert into the
Work row automatically get listed into the Actual Work row
(which then causes all types of problems because the
assumption is a percentage of work done when that isn't
the case).
Can anything be done about this so I can just continue
entering figures into the Work rows without the Actual
Work rows getting populated?
pls advise - Trevor
I'm just getting to know Project 2000 and have set up a
master resource file that is separate from my project
files.
While trying different scenarios from my project folders,
I usually have the screen split to view the gantt chart
and the resource usage view.
The resource usage is set for Work and Actual Work. There
are times when I move the work hours to another date for a
resource leveling scenarios (tweaking). There are other
times when I try this and the figure that insert into the
Work row automatically get listed into the Actual Work row
(which then causes all types of problems because the
assumption is a percentage of work done when that isn't
the case).
Can anything be done about this so I can just continue
entering figures into the Work rows without the Actual
Work rows getting populated?
pls advise - Trevor