B
Bo
I have set up a Master Resource Pool. Each resource has the standard
calendar assigned. As they notify the company of upcoming time off I adjust
their individual calendar. My question is; is there a view that I can look
at by day, week, or month which shows who is taking time off? I really don't
want to have to go into each individuals calendar to see it they have
scheduled time off. I am using MS Project 2000. Thank you in advance.